We've known for ages that we will need to move our VMs to a different physical rack in the data centre, and that means switching IP addresses. We now can't put it off any longer so we've been getting things ready and doing trial migrations.

We have a proxy set up at the new address so we can move in two stages:

1. Switch the DNS records to the new IP :ballot_box_with_check: and wait a couple of days :ballot_box_with_check:
2. Migrate the TA database to the new server:ballot_box_with_check:

Step (2) will entail a short period of downtime — if all goes well it should be less than 15 minutes. We plan to switch the DNS tomorrow morning and then migrate on Wednesday, both at around 07:00 UTC.

We'll update this post with a timeline and any further details along the way.

This room is for discussion about this question.

Once logged in you can direct comments to any contributor here.

Enter question or answer id or url (and optionally further answer ids/urls from the same question) from

Separate each id/url with a space. No need to list your own answers; they will be imported automatically.